Hugel Ave Construction Update

9 months ago

The Hugel Ave construction is well underway and progressing as planned. It is currently estimated that the project is approximately 75% completed. The following work has been completed to date:

- All underground watermain/sanitary/storm pipework is complete

- New watermain has been fully commissioned and is in service

- All curb and sidewalk work has been completed from Russell St to Midland Ave.

- Base course of asphalt has been installed from Russell St to Midland Ave.

The contractor is currently working on the grading of the granular base from Russell St to George St and preparing for the installation of curb and sidewalk on the remainder of the project. The section of Hugel Ave that has been paved will remain closed to traffic while the contractor completes driveway construction and boulevard grading.



Share on Facebook Share on Twitter Share on Linkedin Email this link

You need to be signed in to add your comment.

comment
Submitting your comment
Cancel
Step 9 months ago
It certainly has been very challenging living in this ..i look forward to when it is completed, and the restoration of my property , before it was dug up!!
Share on Facebook Share on Twitter Share on Linkedin Email this link
Rosemary 9 months ago
Awesome! It certainly is worth a little inconvenience.
Share on Facebook Share on Twitter Share on Linkedin Email this link