The reconstruction project on Hugel Avenue, between Midland Avenue and George Street, is nearing completion.

Work completed to date:

  • All underground watermain/sanitary/storm pipework is complete and commissioned.
  • Base and surface course of asphalt has been installed from Midland Avenue to George Street.

  • All curb and sidewalk work has been completed from Midland Avenue to George Street.

  • All topsoil, sod and landscaping work has been completed.

  • Driveways have been reinstated.

  • Street signs have been reinstalled.

At this point all that remains to be done is the line painting and tree planting. The tentative, weather-permitting schedule is for the line painting to be completed this week (Nov. 18-22). The work is expected to only take a couple of hours once crews have favourable conditions to do so. Temporary traffic control will be put in place during this work. The tree planting, to replace trees that were removed during the project, will be completed in Spring 2020.